The developer indicates completion of The Rings by PMR in August 2027: that is the date PMR gave GADAIT in November 2026, and only the date written in your sale and purchase agreement is binding. Many websites still show Q4 2025 or December 2025, the date announced when construction began in November 2023, which was not met; others show Q3 2026 or Q3 2027. In Dubai, payments for an off-plan home are paid into an escrow account governed by Law No. 8 of 2007 and used for the construction of the project. Before reserving, ask the developer in writing for the contractual completion date and the details of the project's escrow account.
The Rings was launched with completion announced for the fourth quarter of 2025. That date has passed and the building is not finished: the Propsearch portal described it as under construction in August 2026. Many listings were never updated, and brokers who did update them do not agree with each other.
| Who says it | Completion shown | Status of the figure |
|---|---|---|
| PMR, the developer, to GADAIT | August 2027 | Information given in November 2026; only the contract is binding |
| Bayut, Sotheby's International Realty, Tanami Properties | Q4 2025 | Launch date, not met |
| Propsearch, FAM Properties | December 2025 | Launch date, not met |
| Insiders of Dubai | Q3 2026 (“planned”) | Broker listing, not sourced |
| Inovo | Q3 2027 | Broker listing, not sourced |
| Some Dubizzle listings | “Ready” | Does not match what the developer told GADAIT |
Listings checked by GADAIT on 26 November 2026; cited by name, not linked. Directional: none of these websites is an official source.
Dubai Law No. 8 of 2007 requires a developer selling off-plan to open an escrow account for the project; buyers' payments are paid into it and allocated to the construction of that project. If a project is not completed, the law provides for the escrow agent, with the Dubai Land Department, to take measures to protect the depositors. An off-plan sale is also registered with the Dubai Land Department, which is when the 4% fee is paid.
The completion date and what happens if it is missed are written in the sale and purchase agreement. Have your lawyer read the delay clause before signing: grace period, notice, and the remedies it gives you.
The project's escrow account number, 1008014829, is published by PMR on its own website; broker listings name Commercial Bank of Dubai as the escrow bank. Check that the payment instructions in your contract point to that account, and have the account verified on the Dubai Land Department's system. GADAIT also asks the developer in writing for the contractual completion date and its grace period, and the latest certified percentage of completion.
With the 30/70 payment plan, 70% of the price is due within one year of completion: if completion moves, that payment moves with it. This is one reason to read the schedule and the delay clause together.
Primary and expert sources behind this answer:
This page is general information, not legal, tax or investment advice. Prices, availability and payment plans come from the developer's documents received on 13 November 2026; a residence can be reserved at any moment and every figure is confirmed again on the day you enquire. Completion dates, fees and visa rules must be checked in the sale and purchase agreement and with the Dubai Land Department for your own case. On this project GADAIT acts with the developer and says so openly. All images are artist's impressions.

Sale mandates for private owners and developers — Marbella, Greece, Dubai, Mauritius, the Maldives and the French Alps. On any given transaction we act for one side, and we say which. Every rate and every fee on this page is sourced (official texts, land registries, tax authorities) and dated; pages are re-verified quarterly.
Our editorial method →No. The developer told GADAIT in November 2026 that completion is expected in August 2027; only the date in the contract is binding. A listing describing The Rings as “ready” does not match that information.
Fourth quarter 2025 was the completion date announced when construction began in November 2023. It was not met, and many listings were not updated.
Into the project's escrow account, as required by Dubai Law No. 8 of 2007 for off-plan sales. PMR publishes the account number, 1008014829, on its website; broker listings name Commercial Bank of Dubai. Have the payment instructions in your contract match it.











GADAIT presents the residences still for sale at The Rings by PMR, with the developer. One advisor confirms availability and price on the day, sends you the brochure and the floor plan, and follows you from reservation to handover.
Newsletter
Be among the privileged.
Subscribe to the Gadait International newsletter and receive the latest trends in the luxury market, along with exclusive opportunities for exceptional properties in advance.
Low frequency. High relevance.